Page 24 - 08.11.2025 Council Packet
P. 24

and walking trails.  Once accepted, the schematic design will lead to the Design Development
                 phase for the building and grounds.
                    During the Design Development phase, the Architectural team will coordinate with the Civil,
                 Structural, and MEP Engineering teams to further develop the schematic design and prepare
                 Design Development level documents. Design Development documents will consist of general
                 plans, sections, elevations, typical construction details, and diagrammatic layouts of building
                 systems to fix and describe the size, function, and character of the project. The Architectural
                 team will also coordinate with the Civil Engineering team and Dry Utility designer to finalize utility
                 plans. Interior Design staff will coordinate with the Town staff to select interior finishes, furniture,
                 fixtures, and equipment (FF&E) based on the project budget.  Following acceptance of the
                 Design Development documents, the project can proceed into the Construction Documents
                 phase.

                    In the Construction Document phase, the Design Development drawings will advance to
                 detailed documents to be issued to the Authorities having jurisdiction (AHJ) for permit review and
                 distributed for bidding and ultimately construction. Complete Construction Specifications,
                 essential to solicit bids and outline the final construction materials, will be developed by all teams
                 in the various scopes of work. The design team will assist the Town in the development of
                 advertisements for bids, attend pre-bid meetings to answer questions and issue any necessary
                 addenda to the project documents, assist in guided pre-bid site visits with potential contractors
                 and ultimately collect, review, and advise the Town in the selection of a contractor or contractors.
                    Following Contractor selection and award of the contract, the project can proceed to
                 construction.  This scale of project is anticipated to take approximately fourteen to eighteen
                 months from groundbreaking to occupancy.


                                                       NEXT STEPS



















                 Figure 4: Graphic timeline of next steps














                                                                 08.11.25 Council Packet Page 24 of 140
              TOWN OF BERLIN COMMUNITY CENTER: FEASIBILITY STUDY                                                    6
   19   20   21   22   23   24   25   26   27   28   29